KMAC PERFORMANCE FACTS
This is not a highlight list. This is all major jobs we've accomplished from our WPO (Wild Peach Office) in 2010.
- Kmac has passed first inspection on 100% of all IRIS jobs we’ve completed.
- Reference contact information can be supplied upon request.
- Click the pdf icon to review our report cards.
HAMMER DOWN!
Job references provided upon request.
BASF Frx 800 Block Recovery TA - January 2010
- Vacuum - Invoiced - 10% below PO
- Hydroblast - Invoiced - 30% below PO
*Click icon to review Report Card filled out by BASF customer rep.
BASF PA E5230 A/B/C - March 2010
- Hydroblast - Invoiced - 9.5% below PO
*Click icon to review Report Card filled out by BASF customer rep.
BASF E5230 D/E/F – April 2010
- Hydroblast Invoiced - 23% below PO
*Click icon to review Report Card filled out by BASF customer rep.
Oxea Pre-Heater – February 2010
- Pre-Heater #4
- Pre-Heater #5
Notes: PH #4 includes 2 days of customer delays (pumps/basket drive motor down), which were billed at discounted rates. PH jobs normally take 5 to 7 days. Kmac has performed both in 2 days. days. Competitor costs runs around $30,000
Ascend Performance Materials – February 2010
This job is normally done in house and takes 8 hours. Kmac did this job in 4 hours, gate to gate, including gate and unit orientations.
References on all jobs can be provided upon request.
|
|